Work DescriptionUpdate
Construction of 1 classroom in the school for students from the higher grades (Size 16ft x 14ft = 224Sft)The columns have been raised for the rooms.They have completed 3 feet of walls.By Monday all the walls will be raised up to lintel level.Centering and bar bending work will be carried out for stair case and lintel and chajjas for windows and door.After casting the above the walls will be raised up to roof level.Centering and bar bending work will be carried out.Approx. by next Saturday 29th June roof will be casted.Further, one course of parapet wall will be constructed.Plastering of outer walls will be done.After removing the centering inside plastering along with electrical work will be done.Laying the tiles for flooring.Then painting and handing over for inside and outside.
One Smart Classroom: Smart class will have a 65 inch LED panel fully touchscreen, and CPU. It will also include one year subscription of the curriculum we offer to kids.Survey is done by the vendor. As and when the room is ready they will install it in 7-10 working days